Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 4.800 | 0.2 | 0.200 | 0.000 |
30W619 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29-01-2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
119.65
Resanction Cost :
119.65
Tentative Cost :
119.65
Exp. Upto Last Fy : 13.94
For CFY 2024-2025
Remaining : 105.71
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 13.94
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
10 years 5 months ago
29 Jan 2014
Tentative Completion date:
6 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
वनभूमि प्रस्ताव संख्या-एफ0पी0/यू0के/रोड़ /26799/2017 दिनांक 28.06.2017 के द्वारा आॅन-लाईन किया गया था, सैद्धान्तिक स्वीकृति प्राप्त। विधिवित स्वीकृति अपेक्षित । कार्यालय अधिशासी अभियन्ता प्रान्तीय खण्ड, लो0नि0वि0 उत्तरकाशी के पत्रांक-1415/वनभूमि दिनांक 11.07.2023 के द्वारा अनुपालन आख्या आॅन लाईन अपलोड कर दी गयी। द्वितीय चरण (स्टेज-।) की स्वीकृति प्राप्त। कार्य प्रगति पर है। -- as on 03-May-2024
Physical Peramenters