Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 2.800 | 2.2 | 2.200 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 24 | 24 | 0.000 | 24 | 24.000 | 0.000 |
30W620 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29-01-2014
TS Amount (lakhs) : 89.93 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
89.93
Resanction Cost :
89.93
Tentative Cost :
89.93
Exp. Upto Last Fy : 39.69
For CFY 2024-2025
Remaining : 50.24
Demand : 25.00
Allotment : 20.00
Exp in CFY : 17.20
Total Up to Date Exp : 56.88
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
10 years 5 months ago
29 Jan 2014
Tentative Completion date:
6 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
विधिवत स्वीकृति प्राप्त है। पहाड़ कटान एवं डम्पिंग जोन हेतु स्वीकृति 3 किमी0 हेतु प्राप्त है। पहाड़ कटान का कार्य 2.80 किमी0 तक पूर्ण। शेष भाग मे विवाद है। -- as on 02-Oct-2022
Physical Peramenters