Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 1.500 | 0.7 | 0.700 | 0.000 |
30W969 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2753/।।।(2)/17-03(एम0एल0ए0)/2017 दि0 11-10-2017
TS Amount (lakhs) : 24.42 Lacs
Financial Detail
Sanction Cost : 24.42 Lacs
Resanction Cost : 24.42 Lacs
Exp. Upto Last Fy : 2.04 Lacs
For CFY 2024-2025
Remaining : 22.38 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.04 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
6 years 7 months ago
11 Oct 2017
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रतिकर वितरण हेतु सहमति/ अनापत्ति प्रमाण पत्र प्राप्त किये जा रहे है। -- as on 03-May-2024
Physical Peramenters