Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 4.025 | 3.000 | 1.025 | 1.025 | 0.000 |
31W129 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शासनादेश संख्याः- 1440/।।। (2)/11-05 (प्रा0आ0)/2010 दि0-28/03/2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 100.80 Lacs
Resanction Cost : 100.80 Lacs
Exp. Upto Last Fy : 73.43 Lacs
For CFY 2024-2025
Remaining : 27.37 Lacs
Demand : 27.37 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 73.43 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
13 years 1 month ago
28 Mar 2011
Tentative Completion date:
5 years 1 month ago
31 Mar 2019
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
भारत सरकार पर्यावरण एवं जलवायु मंत्रालय का पत्रांक 8वी0/यू0सी0पी0/06/57/2021/एफ0सी0/352 दिनांक 13.7.2021 द्वारा सैद्वान्तिक स्वीकृृति प्राप्त। सैद्वान्तिक स्वीकृति में दिये गये बिन्दुओं के अनुपालन हेतु एन0पी0वी0 व वृक्षारोण की धनराशि दिनांक 25.10.2021 द्वारा प्रभागीय वनाधिकारी के पक्ष में आनलाईन जमा कर दी गयी है। सैद्वान्तिक स्वीकृति में अधिरोपित शर्तो की अनुपालन आख्या इस कार्यालय के पत्र सं0 1100/3भू0अ0 दिनांक 08.7.2022 द्वारा प्रभागीय वनाधिकारी उत्तरकाशी वन प्रभाग उत्तरकाशी को विधिवत स्वीकृृति की कार्यवाही हेतु प्रेषित। द्वितीय चरण पार्ट-1 का कार्य 50 प्रतिशत पूर्ण। शेष कार्य प्रगति पर है। विधिवत स्वीकृति अपेक्षित है। -- as on 10-May-2024
Physical Peramenters