Work Profile Report [31W30]

भटवाडी में झाला व हर्षिल के मध्य सियागाड पर पैदल पुल।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : -शा0सं0-121/लो0नि0/04-07(प्रा0आ0)/04 दि0 12.02.2004

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Bridges State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

165.75

Resanction Cost :

165.75

Tentative Cost :

165.75

Exp. Upto Last Fy :

17.40

For CFY 2024-2025

Remaining :

148.35

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

17.40

Survey work done

Sanction on : 20 years 3 weeks ago

02 Dec 2004

Physical Progress:

At start of FY 2024-2025 :

10 %

Up to Date :

95 %

Tentative Completion date on : 3 weeks 3 days ago

30 Nov 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Bridge
1 (105m)
1 (105m)
0 (0.000m)
1 (105m)
1 (105.000m)
0 (0.000m)

Remark

view all

कन्सलटैण्ट द्वारा सेतु की वैटेड डिजाईन/ड्राॅईंग एवं पुनरीक्षित आगणन गठित कर खण्डीय कार्यालय को प्रेषित कर दी गयी थी, जिसे दिनांक-28.05.2024 द्वारा अधीक्षण अभियन्ता के माध्यम से मुख्य अभियन्ता क्षेत्रीय कार्यालय देहरादून को प्रेषित किया गया। पुनरिक्षित आगणन पर मुख्य अभियंता लो0नि0वि0 द्वारा कुछ आपत्तियां लगाकर आगणन वापस किया गया है। आपत्तियों का निराकरण कर कन्सल्टेंट द्वारा माह सितम्बर, 2024 को आगणन (लागत रू0-1144.24 लाख मात्र) खण्ड को प्रेषित किया गया है, जोकि ई-डी0पी0आर0 के माध्यम से शासन को स्वीकृति हेतु प्रेषित किया जाना है। ई-डी0पी0आर0 पोर्टल में आ रही समस्या के कारण आगणन खण्ड स्तर पर लम्बित है। -- as on 24-Oct-2024

Rating : 95

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: