Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 21 | 21 | 0.000 | 21 | 21.000 | 0.000 |
31W605 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शासनादेश सं0 658/।।।(2)/19-03(एम0एल0ए0)/2017 टी.सी. -। दि0 13/फरवरी/2020
TS Amount (lakhs) : 4.4 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.40
Resanction Cost :
4.40
Tentative Cost :
4.40
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 4.40
Demand : 4.40
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
4 years 5 months ago
13 Feb 2020
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य का अनुबन्ध गठित है। कन्सलटेन्ट द्वारा डी0पी0आर0 गठित कर डिजाईन सैल को प्रेषित कर दी गई है। -- as on 02-Mar-2024
Physical Peramenters