Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 1.300 | 0 | 0.000 | 0.000 |
31W639 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 953/।।।(2)/21-03(एम0एल0ए0)/2017 टी.सी. -। दि0 31/03/2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
31.66
Resanction Cost :
31.66
Tentative Cost :
31.66
Exp. Upto Last Fy : 9.55
For CFY 2024-2025
Remaining : 22.11
Demand : 22.11
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 9.55
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
3 years 3 months ago
31 Mar 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण के अन्तर्गत प्रतिकर भुगतान की कार्यवाही गतिमान है। द्वितीय चरण पार्ट-1 का कार्य पूर्ण। -- as on 02-Mar-2024
Physical Peramenters