Work Profile Report [31W639]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश सं0 953/।।।(2)/21-03(एम0एल0ए0)/2017 टी.सी. -। दि0 31/03/2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
31.66
Resanction Cost :
31.66
Tentative Cost :
31.66
Exp. Upto Last Fy :
9.55
For CFY 2024-2025
Remaining :
22.11
Demand :
6.00
Allotment :
0.00
Exp in CFY :
6.38
Total Up to Date Exp :
15.93
Alignment Approved
Sanction on : 3 years 7 months ago
31 Mar 2021
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
55 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण के अन्तर्गत प्रतिकर भुगतान की कार्यवाही गतिमान है। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand