Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
31W70 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शा0सं0- 16 (9)/167/2008 दिनांक 02 मार्च 2009 द्वारा रू 43.77 लाख रू एवं पुनःरीक्षित स्वीकृृति -शा0सं0- 13 (1)/2017/167/2009 दिनांक 30 मार्च 2017 द्वारा रू 94.65 लाख।
TS Amount (lakhs) : 94.65 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
43.77
Resanction Cost :
94.65
Tentative Cost :
94.65
Exp. Upto Last Fy : 91.38
For CFY 2024-2025
Remaining : 3.27
Demand : 3.27
Allotment : 3.27
Exp in CFY : 0.00
Total Up to Date Exp : 91.38
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
15 years 3 months ago
21 Mar 2009
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्वों का भुगतान शेष। -- as on 31-Mar-2023
Physical Peramenters