Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.675 | 1.675 | 0.000 | 1.675 | 1.670 | 0.000 |
31W709 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला ग्राम्य विकास अभिकरण उत्तरकाशी के पत्रांक 384/बी0ए0डी0पी0/यो0प्रा0/2022-23 दि0 24/10/2022
TS Amount (lakhs) : 70 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
70.00
Resanction Cost :
70.00
Tentative Cost :
70.00
Exp. Upto Last Fy : 13.76
For CFY 2024-2025
Remaining : 56.24
Demand : 56.24
Allotment : 56.24
Exp in CFY : 6.16
Total Up to Date Exp : 19.92
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 8 months ago
24 Oct 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अधीक्षण अभियंता के पत्रांक 4472/821 सी0-6/2022-23 दिनांक 03/11/2022 द्वारा समरेखण अनुमोदित। कार्य प्रगति पर है। -- as on 04-Feb-2023
Physical Peramenters