Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.025 | 4.025 | 3.000 | 1.025 | 1.025 | 0.000 |
31W774 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 ई0 फाईल सं0 45771 लो0नि0वि0 अनुभाग 2 दि0 28 फरवरी 2023
TS Amount (lakhs) : 128 Lacs
Financial Detail
Sanction Cost : 128.00 Lacs
Resanction Cost : 128.00 Lacs
Exp. Upto Last Fy : 33.84 Lacs
For CFY 2024-2025
Remaining : 94.16 Lacs
Demand : 50.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 33.84 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
1 year 2 months ago
28 Feb 2023
Tentative Completion date:
3 months 1 week from now
30 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण पार्ट-1 का कार्य 75 प्रतिशत पूर्ण। शेष कार्य प्रगति पर है। -- as on 03-Apr-2024
Physical Peramenters