Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 0 | 0 | 0 | 0 |
32W1158 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : नाबार्ड का पत्रांक आर. 16 आर.आई.डी.एफ.-27 101 आईएससी - 20.01.2022, दिनांक 11.03.2022
TS Amount (lakhs) : 330.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
318.78
Resanction Cost :
354.20
Tentative Cost :
318.78
Saving
35.42
Exp. Upto Last Fy : 280.49
For CFY 2024-2025
Remaining : 73.71
Demand : 20.00
Allotment : 20.00
Exp in CFY : 0.70
Total Up to Date Exp : 281.19
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
3 years 5 months ago
27 Jan 2021
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 कि.मी. के सापेक्ष 4.70 कि.मी. पहाड़ कटान एवं द्वितीय चरण के कार्य पूर्ण। मात्र 0.30 कि.मी. में पहाड़ कटान का कार्य प्रगति पर है। ऊध्र्वाधर एवं भारी चट्टान होने के कारण भौतिक प्रगति अपेक्षा अनुरूप नही है। पहाड़ कटान का कार्य प्रगति पर। -- as on 06-Mar-2024
Physical Peramenters