Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 22 | 22 | 22.000 | 0 | 0.000 | 0.000 |
32W1230 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. E-file no. 38540, dt. 29-03-2023
TS Amount (lakhs) : 273.8 Lacs
Financial Detail
Sanction Cost : 273.80 Lacs
Resanction Cost : 294.34 Lacs
Exp. Upto Last Fy : 254.44 Lacs
For CFY 2024-2025
Remaining : 39.90 Lacs
Demand : 28.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 254.44 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
1 year 1 month ago
29 Mar 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उक्त कार्य नाबार्ड के पत्रांक राबै उत्त.क्षे.का. एसपीडी 1155 आर..16 आरआईडीएफ-29 122 आईएससी., दिनांक 21.08.2023 द्वारा नाबार्ड-29 में स्वीकृत। 22.00 कि.मी. पी.सी. के सापेक्ष 22.00 कि.मी. में पी.सी. का कार्य पूर्ण। दायित्वों का भुगतान शेष। अन्य सिविल कार्य प्रगति पर। -- as on 13-Dec-2023
Physical Peramenters