Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4.29 | 0.000 | 4.29 | 0.000 | 0.000 |
32W1305 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, उत्तराखण्ड लो.नि.वि., देहरादून का पत्रांक 191/14 याता (क)-उ./2023, दिनांक 09.02.2024
TS Amount (lakhs) : 64.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.29
Resanction Cost :
64.29
Tentative Cost :
64.29
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 64.29
Demand : 64.29
Allotment : 40.00
Exp in CFY : 30.12
Total Up to Date Exp : 30.12
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
5 months 1 week ago
09 Feb 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। कार्य प्रगति पर। -- as on 24-Apr-2024
Physical Peramenters