Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
32W923 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शाशनादेश संख्या 1640 ए./।।। (2)/18-02 (एम0एल0ए0)/2017, दिनांक 24.04.2018
TS Amount (lakhs) : 86.52 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
86.52
Resanction Cost :
86.52
Tentative Cost :
86.52
Exp. Upto Last Fy : 78.04
For CFY 2024-2025
Remaining : 8.48
Demand : 8.35
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 78.04
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
6 years 2 months ago
24 Apr 2018
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण की स्वीकृति प्राप्त। प्रतिकर वितरण की कार्यवाही प्रगति पर। -- as on 19-Apr-2023
Physical Peramenters