Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7 | 0 |
33W1174 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0 905/।।।(2)/21-08 प्रा0आ0 /2018 दिनांक 30 मार्च 2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 73.77 Lacs
Resanction Cost : 73.77 Lacs
Exp. Upto Last Fy : 17.58 Lacs
For CFY 2024-2025
Remaining : 56.19 Lacs
Demand : 11.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 17.58 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
30 Mar 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जिलाधिकारी उत्तरकाशी के पत्रांक 824/11-विविध(2022-23) दिनांक 01/09/2023 के द्वारा मार्ग निर्माण हेतु वृक्ष विहीन सिविल सोयम भूमि को लो0नि0वि0 पुरोला के नाम हस्तान्तारण की स्वीकृति प्रदान की गयी है।डी0पी0आर0 इस कार्यालय के पत्रांक 2507/13सी दिनांक 12-12-2023 के द्वारा लम्बाई 5 कि0मी0 लागत रू0 254.72 लाख की वृत्तीय कार्यालय को प्रेषित।तथा अधीक्षण अभियंता के पत्रांक सं0 5745/20 बजट-06/2024 दिनांक 20/01/2024 के द्वारा इस खण्ड को आपत्ति में प्राप्त। -- as on 05-Feb-2024
Physical Peramenters