Work Profile Report [33W1222]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6171/III(2)/21-02(प्रा0आ0)/2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.18
Resanction Cost :
3.18
Tentative Cost :
3.18
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
3.18
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 3 years 3 months ago
22 Dec 2021
Physical Progress:
At start of FY 2025-2026 :
76 %
Up to Date :
80 %
Tentative Completion date on : 1 year 7 months ago
31 Aug 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ई0डी0पी0आर0 गठित की जानी है। -- as on 04-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: