Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
33W1363 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E fil e no. 48419
TS Amount (lakhs) : 187.68 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
187.68
Resanction Cost :
187.68
Tentative Cost :
187.68
Exp. Upto Last Fy : 74.70
For CFY 2024-2025
Remaining : 112.98
Demand : 112.98
Allotment : 51.00
Exp in CFY : 52.52
Total Up to Date Exp : 127.21
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 95 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
11 months 2 days from now
20 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पुर्ण। शेष प्रगति पर है। -- as on 10-May-2024
Physical Peramenters