Work Profile Report [33W18]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 435/1/।।।-2/05 दिनांक 24-2-06
TS Amount (lakhs) : 29.4 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.40
Resanction Cost :
29.40
Tentative Cost :
29.40
Exp. Upto Last Fy :
16.03
For CFY 2025-2026
Remaining :
13.37
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
16.03
Construction Started
Sanction on : 19 years 1 month ago
24 Feb 2006
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
55 %
Tentative Completion date on : 1 year 11 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समरेखण स्वीकृत, भूमि प्रतिकर की कार्यवाही की जा रही है। -- as on 31-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand