Work Profile Report [33W18]

जखोल से धारा मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं0 435/1/।।।-2/05 दिनांक 24-2-06

TS Amount (lakhs) : 29.4 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

29.40

Resanction Cost :

29.40

Tentative Cost :

29.40

Exp. Upto Last Fy :

16.03

For CFY 2025-2026

Remaining :

13.37

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

16.03

Construction Started

Sanction on : 19 years 1 month ago

24 Feb 2006

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

55 %

Tentative Completion date on : 1 year 11 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
1.5
1
1
-

Remark

view all

समरेखण स्वीकृत, भूमि प्रतिकर की कार्यवाही की जा रही है। -- as on 31-Dec-2024

Rating : 68

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: