Work Profile Report [34W1093]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई-फाईल संख्या- 84809/02 लोक निर्माण अनुभाग-2 देहरादून दि0 02.09.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
16.80
Resanction Cost :
16.80
Tentative Cost :
16.80
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
16.80
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 4 months 17 hours ago
02 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 7 months 3 weeks from now
30 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण कार्य हेतु निविदा आमन्त्रित। दिनांक 29.09.2025 को निविदा खोली जायेगी। Survey work done. -- as on 28-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: