Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 2.15 | 2.15 | 0 |
34W672 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 5603/।।।(2)/15-30 (प्रा0आ0) /2015 दिनांक 28.7.2015
TS Amount (lakhs) : 58.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.59
Resanction Cost :
58.59
Tentative Cost :
58.59
Exp. Upto Last Fy : 1.58
For CFY 2024-2025
Remaining : 57.01
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.58
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 100 %
Sanction on :
8 years 11 months ago
28 Jul 2015
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
सैद्धान्तिक स्वीकृति प्राप्त। विधिवत स्वीकृति हेतु अनुपालन आख्या प्रभागीय वनाधिकारी को प्रेषित। -- as on 14-Apr-2023
Physical Peramenters