Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.8 | 6.8 | 6.8 | 0 |
34W905 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2266(।)/।।।(2)/20-02(एम.एल.एल)/2017 टी.सी. दिनांक 22.12.2020
TS Amount (lakhs) : 396.98 Lacs
Financial Detail
Sanction Cost : 396.98 Lacs
Resanction Cost : 396.98 Lacs
Exp. Upto Last Fy : 374.24 Lacs
For CFY 2024-2025
Remaining : 22.74 Lacs
Demand : 22.74 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 374.24 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
3 years 4 months ago
22 Dec 2020
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
6.8 km road work complete. minor bridge work in progress. -- as on 18-Dec-2023
Physical Peramenters