Work Profile Report [34W905]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश सं0 2266(।)/।।।(2)/20-02(एम.एल.एल)/2017 टी.सी. दिनांक 22.12.2020
TS Amount (lakhs) : 396.98 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
396.98
Resanction Cost :
396.98
Tentative Cost :
396.98
Exp. Upto Last Fy :
374.24
For CFY 2024-2025
Remaining :
22.74
Demand :
22.74
Allotment :
0.00
Exp in CFY :
15.20
Total Up to Date Exp :
389.44
In Maintenance After Completion
Sanction on : 3 years 11 months ago
22 Dec 2020
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
work completed. -- as on 17-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: