Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7 | 0 |
34W969 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5999/।।।(2)/21-08(प्रा0आ0)/2017 टी0सी0 दिनांक 10.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
73.50
Resanction Cost :
73.50
Tentative Cost :
73.50
Exp. Upto Last Fy : 2.70
For CFY 2024-2025
Remaining : 70.80
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.70
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
2 years 7 months ago
10 Dec 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Survey work completed. -- as on 12-Jul-2024
Physical Peramenters