Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 7.675 | 7.675 | 0 |
36W207 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6970/।।। (2)/13-40 (प्रा.आ.)/2013 दिनांक 14 दिसम्बर 2013
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 93.60 Lacs
Resanction Cost : 93.60 Lacs
Exp. Upto Last Fy : 5.44 Lacs
For CFY 2024-2025
Remaining : 88.16 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5.44 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 5 months ago
14 Dec 2013
Tentative Completion date:
3 months 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 10: In Principal approval
Bottelneck: no issue
एन०पी०वी० भुगतान हेतु आवंटन प्राप्त। भुगतान की कार्यवाही की जा रही है। -- as on 30-Nov-2023
Physical Peramenters