Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.6 | 1.025 | 1.025 | 0 |
36W354 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 464/।।।(2)/20-6(एम॰एल॰ए॰)/2017 दिनांक 29 जनवरी, 2020
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 24.80 Lacs
Resanction Cost : 24.80 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 24.80 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 years 3 months ago
29 Jan 2020
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
डी॰एफ॰ओ॰ बद्रीनाथ वन प्रभाग गोपेश्वर के पत्रांक 1132/12-1 दिनांक गोपेश्वर 28.08.2023 द्वारा वन संरक्षक पौड़ी को प्रेषित। वर्तमान में प्रस्ताव नोडल स्तर पर लम्बित। -- as on 31-Jan-2024
Physical Peramenters