Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.925 | 1.925 | 1.925 | 0 |
36W396 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3196(1)/।।।(2)/21-05 (एम॰एल॰ए॰)/ 2017 टी॰सी॰-।। दिनांक 26 अगस्त, 2021
TS Amount (lakhs) : 22.24 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
83.90
Resanction Cost :
83.90
Tentative Cost :
83.90
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 83.90
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 10 months ago
26 Aug 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
वनभ्ूामि हस्तान्तरण प्रस्ताव गठित किये जाने के अन्तर्गत क्षतिपूरक वृक्षारोपण हेतु भूमि उपलब्ध कराने के लिए इस कार्यालय के पत्रांक 408/10एल॰ए॰ दिनांक 20.02.2024 द्वारा जिलाधिकारी, चमोली को पत्र प्रेषित। -- as on 29-Feb-2024
Physical Peramenters