Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 | ||
No of Bridges | 2 | 2 | 2 | 0 | ||
Span of Bridges [m] | 22 | 22 | 22 | 0 |
36W397 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3591(1)/।।।(2)/21-05 (एम॰एल॰ए॰)/ 2017 टी॰सी॰ दिनांक 10 सितम्बर, 2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 82.50 Lacs
Resanction Cost : 82.50 Lacs
Exp. Upto Last Fy : 0.48 Lacs
For CFY 2024-2025
Remaining : 82.02 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.48 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 8 months ago
10 Sep 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: Alignment Dispute
भूगर्भीय आख्या दिनांक 28.03.2024 को प्राप्त। मार्ग का संरेखण प्रस्ताव गठित किया जा रहा है। -- as on 30-Mar-2024
Physical Peramenters