Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
36W403 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6586(1)/।।।(2)/21-05 (एम॰एल॰ए॰)/ 2017 टी॰सी॰।। दिनांक 31 दिसम्बर, 2021
TS Amount (lakhs) : 2.66 Lacs
Financial Detail
Sanction Cost : 51.60 Lacs
Resanction Cost : 51.60 Lacs
Exp. Upto Last Fy : 0.24 Lacs
For CFY 2024-2025
Remaining : 51.36 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.12 Lacs
Total Up to Date Exp : 0.35 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 4 months ago
31 Dec 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: CA Land
दोगुना क्षेत्रफल का उपयुक्तता प्रमाण-पत्र उपलब्ध कराने हेतु इस कार्यालय के पत्रांक 318/10 एल॰ए॰ दिनांक 12.02.2024 द्वारा डी॰एफ॰ओ॰, गोपेश्वर को पत्र प्रेषित. -- as on 29-Feb-2024
Physical Peramenters