Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 0.95 | 0.95 | 0 |
36W404 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6586(1)/।।।(2)/21-05 (एम॰एल॰ए॰)/ 2017 टी॰सी॰।। दिनांक 31 दिसम्बर, 2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.80
Resanction Cost :
25.80
Tentative Cost :
25.80
Exp. Upto Last Fy : 0.37
For CFY 2024-2025
Remaining : 25.43
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.37
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 6 months ago
31 Dec 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य का द्वितीय चरण का आगणन अधीक्षण अभियन्ता, सातवाॅ वृत्त लो॰नि॰वि॰, गोपेश्वर के पत्रांक 1209/483 याता-7/2024 दिनांक 15.04.2024 द्वारा मुख्य अभियन्ता, लो॰नि॰वि॰, पौड़ी कोे प्रेषित। -- as on 01-May-2024
Physical Peramenters