Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
36W428 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 46275 दिनांक 14.02.2023
TS Amount (lakhs) : 3.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.75
Resanction Cost :
3.75
Tentative Cost :
3.75
Exp. Upto Last Fy : 0.68
For CFY 2024-2025
Remaining : 3.07
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.68
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 5 months ago
14 Feb 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
संयुक्त निरीक्षण आख्या दिनांक 05.03.2024 को प्राप्त। लैण्ड शैड्यूल तैयार किया जा रहा है। -- as on 31-May-2024
Physical Peramenters