Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.5 | 0 |
36W451 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 26616 एवं कम्प्यूटर जनित संख्या 163736/2023 दिनांक 23.10.2023
TS Amount (lakhs) : 5.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5.25
Resanction Cost :
5.25
Tentative Cost :
5.25
Exp. Upto Last Fy : 0.89
For CFY 2024-2025
Remaining : 4.36
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.89
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 months 3 weeks ago
23 Oct 2023
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
संरेखण प्रस्ताव पर अधीक्षण अभियन्ता, सातवां वृत्त, लो॰नि॰वि॰, गोपेश्वर के पत्रांक 2223/629 याता॰-07/2023 दिनांक 11.06.2024 द्वारा आपत्तियां लगायी गयी हैं। आपत्तियों का निराकरण किया जा रहा है। -- as on 01-Jul-2024
Physical Peramenters