Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.4 | 0.4 | 0.400 | 0 | 0.000 | 0.000 |
37W464 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 611/D.P./2021-22
TS Amount (lakhs) : 3.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy : 9.82
For CFY 2024-2025
Remaining : 0.18
Demand : 0.40
Allotment : 0.18
Exp in CFY : 0.00
Total Up to Date Exp : 9.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 10 months ago
29 Aug 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 30-Mar-2024
Physical Peramenters