Work Profile Report [37W504]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य विकास अधिकारी, चमोली का पत्रांकः- 225/जि0यो0/2023-24 दिनांक 01.06.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7.00
Resanction Cost :
7.00
Tentative Cost :
7.00
Exp. Upto Last Fy :
5.60
For CFY 2024-2025
Remaining :
1.40
Demand :
1.40
Allotment :
1.40
Exp in CFY :
0.00
Total Up to Date Exp :
5.60
Construction Started
Sanction on : 1 year 5 months ago
01 Jun 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
20 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में। -- as on 25-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand