Work Profile Report [38W738]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E file No. 52001/06 Lok Nirman Anubhag-2 Dt. 12/03/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
115.90
Resanction Cost :
115.90
Tentative Cost :
155.90
(-) Counted Excess
-40.00
Exp. Upto Last Fy :
0.07
For CFY 2025-2026
Remaining :
115.83
Demand :
110.00
Allotment :
50.00
Exp in CFY :
26.61
Total Up to Date Exp :
26.68
Construction Started
Sanction on : 9 months 3 days ago
12 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
20 %
Tentative Completion date on : 5 months 2 weeks from now
31 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 40 has been counted as tentative cost increased from 115.9 to 155.9 . -- as on 08-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: