Work Profile Report [38W755]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E file No. 49189/05 Dt. 04/08/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NandDevi Rajjat ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
523.29
Resanction Cost :
523.29
Tentative Cost :
523.29
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
523.29
Demand :
250.00
Allotment :
210.10
Exp in CFY :
24.78
Total Up to Date Exp :
24.78
Construction Started
Sanction on : 5 months 2 weeks ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
20 %
Tentative Completion date on : 5 months 6 days from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार, स्कपर, नाली, सुपरऐलीवेशन एवं सोलिंग एकत्रीकरण का कार्य प्रगति में। किमी0 5 व 6 में जी-1 का कार्य पूर्ण। -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: