Work Profile Report [38W76]

जनपद चमोली में कपीरी-नैनीसैंण -किमोली गांव तक मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0ः- 2538/।।।(2)/08-42 (प्रा0आ0)/07टी0सी0 दि0 17.7.08

TS Amount (lakhs) : 88.55 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

91.87

Resanction Cost :

91.87

Tentative Cost :

91.87

Exp. Upto Last Fy :

83.95

For CFY 2024-2025

Remaining :

7.92

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

83.95

Work completed

Sanction on : 16 years 4 months ago

17 Jul 2008

Physical Progress:

At start of FY 2024-2025 :

90 %

Up to Date :

100 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2.5
2.5
2.5
-

Remark

view all

fक0मी0 2.00 fक0मी0 में पहाड़ कटान एवं पार्ट-।। का कार्य पूर्ण। fक.मी. 2.00 से 2.50 में संरेखण fववाद। मुख्य अभि0 पौड़ी के प0 3495/73 नाबार्ड्र (पी0सी0आर0)/2020 दि0 25.11.2020 द्वारा प्रमुख अभि0 को प्रेषित। -- as on 31-Mar-2021

Rating : 104

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: