Work Profile Report [38W76]

जनपद चमोली में कपीरी-नैनीसैंण -किमोली गांव तक मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0ः- 2538/।।।(2)/08-42 (प्रा0आ0)/07टी0सी0 दि0 17.7.08

TS Amount (lakhs) : 88.55 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

91.87

Resanction Cost :

91.87

Tentative Cost :

91.85

Saving

0.02

Exp. Upto Last Fy :

83.95

For CFY 2025-2026

Remaining :

7.92

Demand :

7.90

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

83.95

Work completed

Sanction on : 17 years 4 months ago

17 Jul 2008

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 8 months 2 weeks ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
2.5
2.5
2.5
-

Remark

view all

Overall Saving 0.02 has been recorded as expected cost of work reduced from 91.87 to 91.85 . -- as on 07-Dec-2025

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: