Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12.25 | 12.25 | 0.000 | 12.25 | 6.000 | 8.000 |
39W1007 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 271.49 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
271.49
Resanction Cost :
271.49
Tentative Cost :
271.49
Exp. Upto Last Fy : 0.57
For CFY 2024-2025
Remaining : 270.92
Demand : 150.00
Allotment : 50.00
Exp in CFY : 61.82
Total Up to Date Exp : 62.39
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 70 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
8 किमी0 में पीसी कार्य पूर्ण। शेष दीवार एवं नाली निर्माण का कार्य प्रगति में। -- as on 01-Jul-2024