Work Profile Report [39W1024]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. ।/41204/2023 ई-फाइल सं0-50408 लोक निर्माण अनुभाग-2 दिनांक 27.07.2023
TS Amount (lakhs) : 216.39 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
216.56
Resanction Cost :
216.56
Tentative Cost :
216.56
Exp. Upto Last Fy :
29.19
For CFY 2024-2025
Remaining :
187.37
Demand :
150.19
Allotment :
140.64
Exp in CFY :
140.64
Total Up to Date Exp :
169.84
Work completed
Sanction on : 1 year 4 months ago
27 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
100 %
Tentative Completion date on : 3 months 1 week ago
13 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.50 किमी0 में पीसी का कार्य पूर्ण। किमी0 1,2 व 3 में दीवार निर्माण, 8 नं0 स्कपर का निर्माण कार्य पूर्ण। -- as on 28-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand