Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 2.500 | 0.000 |
39W1024 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/41204/2023 ई-फाइल सं0-50408 लोक निर्माण अनुभाग-2 दिनांक 27.07.2023
TS Amount (lakhs) : 216.39 Lacs
Financial Detail
Sanction Cost : 216.56 Lacs
Resanction Cost : 216.56 Lacs
Exp. Upto Last Fy : 29.19 Lacs
For CFY 2024-2025
Remaining : 187.37 Lacs
Demand : 187.00 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 57.24 Lacs
Total Up to Date Exp : 86.43 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
9 months 3 weeks ago
27 Jul 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
किमी0 1 व 2 में दीवार निर्माण, 3 नं0 स्कपर का निर्माण कार्य पूर्ण। 2.50 किमी0 में सोलिग कोट व 1.50 किमी0 में इण्टर कोट का कार्य पूर्ण। शेष कार्य प्रगति में। -- as on 01-May-2024
Physical Peramenters