Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.25 | 3.25 | 0.000 | 3.25 | 3.250 | 0.000 |
39W1025 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/41204/2023 ई-फाइल सं0-50408 लोक निर्माण अनुभाग-2 दिनांक 27.07.2023
TS Amount (lakhs) : 217.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
217.42
Resanction Cost :
217.42
Tentative Cost :
217.42
Exp. Upto Last Fy : 31.50
For CFY 2024-2025
Remaining : 185.92
Demand : 185.00
Allotment : 17.68
Exp in CFY : 17.68
Total Up to Date Exp : 49.17
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 45 %
Sanction on :
11 months 2 weeks ago
27 Jul 2023
Tentative Completion date:
3 months 1 week from now
28 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.25 किमी0 सोलिंग, इण्टर एवं 1.25 किमी0 टाॅप कोट का कार्य पूर्ण।
स्कपर निर्माण कार्य पूर्ण। दीवार निर्माण् एवं शेष टाॅप कोट का कार्य प्रगति पर।
-- as on 25-Jun-2024
Physical Peramenters