Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 5.000 |
39W1027 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/41204/2023 ई-फाइल सं0-50408 लोक निर्माण अनुभाग-2 दिनांक 27.07.2023
TS Amount (lakhs) : 274.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
274.26
Resanction Cost :
274.26
Tentative Cost :
274.26
Exp. Upto Last Fy : 105.57
For CFY 2024-2025
Remaining : 168.69
Demand : 168.00
Allotment : 16.82
Exp in CFY : 16.81
Total Up to Date Exp : 122.38
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 90 %
Sanction on :
11 months 2 weeks ago
27 Jul 2023
Tentative Completion date:
1 month 3 weeks from now
13 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 किमी0 में PC का कार्य पूर्ण। पैरापिट, साइनबोर्ड, किमी0 स्टोन का कार्य प्रगति मंे। -- as on 25-Jun-2024