Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
39W1034 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 1/167414/2023 ई-फाइल सं0-63235 लोक निर्माण अनुभाग-2 दिनांक 07.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy : 0.09
For CFY 2024-2025
Remaining : 4.41
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.09
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 months 1 week ago
07 Nov 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वे का कार्य किया जाना है। -- as on 08-Nov-2023
Physical Peramenters