Work Profile Report : 39W1140
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा.सं. सं0 1/266914/2025 ई-फाइल संख्या 50408 /लोक निर्माण अनुभाग-2 दिनांक 08.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
243.44
Resanction Cost :
243.44
Tentative Cost :
243.44
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
243.35
Demand :
139.08
Allotment :
139.08
Exp in CFY :
110.44
Total Up to Date Exp :
110.53
Construction Started
Sanction on : 1 year 1 month ago
08 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
40 %
Tentative Completion date on : 4 months 2 weeks from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.00 किमी0 में सोलिंग कोट & Inter Coat का कार्य पूर्ण। 1.00 किमी0 में Top Complete. others कार्य प्रगति पर। -- as on 01-Jul-2025