Work Profile Report [39W1149]
Tenders
Aggrements
Project Activities
alerts
Administrative Approval Detail : शा.सं. सं0 1/319509/2025 ई-पत्रावली संख्या 5040850408 /लोक निर्माण अनुभाग-2 दिनांक 04.08.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
444.66
Resanction Cost :
444.66
Tentative Cost :
444.66
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
444.66
Demand :
127.33
Allotment :
89.21
Exp in CFY :
42.33
Total Up to Date Exp :
42.33
Construction Started
Sanction on : 5 months 2 weeks ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
25 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रैश बरियर, स्कपर दीवारें व नाली कार्य प्रगति पर हैं। -- as on 20-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: