Work Profile Report : 39W1212
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा.सं. सं0 1/332835/2025 ई-फाइल संख्या 77131/07 /लोक निर्माण अनुभाग-2 दिनांक 23.09.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
67.10
Resanction Cost :
67.10
Tentative Cost :
67.10
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
67.10
Demand :
50.00
Allotment :
50.00
Exp in CFY :
38.53
Total Up to Date Exp :
38.53
Construction Started
Sanction on : 4 months 2 weeks ago
23 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 4 months 2 weeks from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.00 किमी0 में पहाड कटान कार्य पूर्ण। शेष पहाड कटज्ञन कार्य प्रगति में। -- as on 03-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: