Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
39W224 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6985/।।।(2)/10-18(प्रा0आ0)/2010 टी0सी0-4 दिनांक 03.02.2011
TS Amount (lakhs) : 1.83 Lacs
Financial Detail
Sanction Cost : 37.80 Lacs
Resanction Cost : 37.80 Lacs
Exp. Upto Last Fy : 25.07 Lacs
For CFY 2024-2025
Remaining : 12.73 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 25.07 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
13 years 3 months ago
03 Feb 2011
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
वनभूमि की सैद्धान्तिक स्वीकृति भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/95/2021/एफसी/1101 दिनांक 29.11.2021 द्वारा प्राप्त है। एनपीवी की धनराशि जमा की जा चुकी है। सैद्धान्तिक स्वीकृति की अनुपालन आख्या इस कार्यालय के पत्र संख्या 3514/16सी दिनांक 23.09.2022 द्वारा डीएफआ को प्रेषित है। विधिवत स्वीकृति अपेक्षित है। द्वितीय चरण के अन्तर्गत कार्य पूर्ण। -- as on 03-May-2024
Physical Peramenters