Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
39W232 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1430/।।।(2)/11-04(मु.मं.घो.)/2011 दिनांक 25.03.2011
TS Amount (lakhs) : 12.24 Lacs
Financial Detail
Sanction Cost : 63.00 Lacs
Resanction Cost : 63.00 Lacs
Exp. Upto Last Fy : 24.08 Lacs
For CFY 2024-2025
Remaining : 38.92 Lacs
Demand : 15.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 24.08 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
13 years 1 month ago
25 Mar 2011
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 10: In Principal approval
Bottelneck: no issue
वनभूमि की पत्र संख्या 1793 दिनांक 31.01.2018 द्वारा सैद्धान्तिक स्वीकृति प्राप्त। एनपीवी की धनराशि जमा की जा चुकी है। विधिवत स्वीकृति अपेकि्षत है। पुनः इस कार्यालय के पत्र संख्या 1761/16सी दिनांक 23.05.2022 द्वारा विधिवत स्वीकृति हेतु डीएफओ को लिखा गया है। पत्र संख्या 153/16सी दिनांक 16.01.2024 द्वारा एनपीवी की अतिरिक्त धनराशि रू0 1402890.00 की मांग प्रमुख अभियन्ता से की गयी है। दि्वतीय चरण की स्वीकृति के अन्तर्गत कार्य पूर्ण। एनपीवी की बढ़ी हुई धनराशि जमा करने हेतु पुनः इस कार्यालय के पत्र संख्या 1185/16सी दिनांक 07.05.2024 द्वारा प्रमुख अभियन्ता एवं विभागाध्यक्ष से धनराशि की मांग की गयी है। -- as on 10-May-2024
Physical Peramenters