Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 85 | 85 | 85 | 0 |
39W470 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 935/18-(2)/15-12(11)/2014टी.सी. दिनांक 30.03.2015
TS Amount (lakhs) : 377.51 Lacs
Financial Detail
Sanction Cost : 377.51 Lacs
Resanction Cost : 377.51 Lacs
Exp. Upto Last Fy : 196.19 Lacs
For CFY 2024-2025
Remaining : 181.32 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 196.19 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
9 years 1 month ago
30 Mar 2015
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 10: In Principal approval
Bottelneck: no issue
उत्तराखण्ड शासन के पत्र संख्या 506/एक्स-4-15/1(25)/2015 दिनांक 06.01.2016 द्वारा विधिवत स्वीकृति प्राप्त।
बांये ओर के एबटमेन्ट का कार्य 90 प्रतिशत पूर्ण। दांयी ओर के एबटमेन्ट की नींव खुदाई के दौरान कठोर चट्टान दृष्टिगत होने के कारण कन्स्टलटेन्ट से स्थलीय निरीक्षण कराया गया, जिसके उपरान्त कन्सलटेन्ट द्वारा दांये एबटमेन्ट का डिजाइन संशोधित करने का परामर्श दिया गया। कन्स्लटेन्ट से संशोधित डिजाइन प्राप्त किया जा रहा है।
-- as on 13-May-2024
Physical Peramenters