Work Profile Report [39W687]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 8113/।।।(2)/18-08 (एम.एल.ए.)/2017 दिनांक 31.12.2018
TS Amount (lakhs) : 8.48 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
19.29
Resanction Cost :
19.29
Tentative Cost :
19.29
Exp. Upto Last Fy :
6.24
For CFY 2025-2026
Remaining :
13.05
Demand :
0.50
Allotment :
0.09
Exp in CFY :
0.00
Total Up to Date Exp :
6.24
Construction Started
Sanction on : 7 years 3 weeks ago
31 Dec 2018
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 2 years 2 months from now
31 Mar 2028
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण की स्वीकृति के अन्तर्गत नापभूमि में कार्य पूर्ण।प्रतिकर वितरण हेतु अभिलेख मांगे गये हैं। -- as on 02-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand