Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
39W772 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 629(1)/।।।(2)/21-08(एमएलए)/2017टीसी-। दिनांक 20.03.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.95
Resanction Cost :
34.95
Tentative Cost :
34.95
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 34.95
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 years 3 months ago
20 Mar 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण की स्वीकृति के अन्तर्गत कार्य पूर्ण। मुआवजा वितरण शेष है। -- as on 30-Aug-2023
Physical Peramenters