Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 2.000 | 3 | 3.000 | 0.000 |
39W773 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 630(1)/।।।(2)/21-08(एमएलए)/2017टीसी-।। दिनांक 20.03.2021
TS Amount (lakhs) : 341.17 Lacs
Financial Detail
Sanction Cost : 341.17 Lacs
Resanction Cost : 341.17 Lacs
Exp. Upto Last Fy : 250.36 Lacs
For CFY 2024-2025
Remaining : 90.81 Lacs
Demand : 90.83 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 250.36 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
3 years 1 month ago
20 Mar 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 किमी0 में पहाड कटान व स्कपर निर्माण कार्य पूर्ण एवं 2.00 किमी0 में दीवार निर्माण कार्य पूर्ण। शेष दीवार निर्माण कार्य प्रगति में। -- as on 06-Mar-2024
Physical Peramenters