Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 2.000 | 3 | 3.000 | 3.000 |
39W773 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 630(1)/।।।(2)/21-08(एमएलए)/2017टीसी-।। दिनांक 20.03.2021
TS Amount (lakhs) : 341.17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
341.17
Resanction Cost :
341.17
Tentative Cost :
341.17
Exp. Upto Last Fy : 250.36
For CFY 2024-2025
Remaining : 90.81
Demand : 90.83
Allotment : 90.83
Exp in CFY : 39.30
Total Up to Date Exp : 289.66
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
3 years 3 months ago
20 Mar 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 किमी0 में पहाड कटान व दीवार निर्माण कार्य पूर्ण। पैरापिट व नाली निर्माण कार्य प्रगति में। -- as on 14-Jul-2024
Physical Peramenters