Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 0.000 | 0.000 |
39W800 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3572(1)/।।।(2)/21-08(एम.एल.ए.)/2017 टी.सी.-।। दिनांक 10.09.2021
TS Amount (lakhs) : 3.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
57.62
Resanction Cost :
57.62
Tentative Cost :
57.62
Exp. Upto Last Fy : 0.87
For CFY 2024-2025
Remaining : 56.75
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.87
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 10 months ago
10 Sep 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
सवे कार्य पूर्ण। ग्रामीणों की अनापत्ति प्राप्त है। भू वैज्ञानिक द्वारा निरीक्षण कर लिया गया है। आख्या अपेक्षित है। तदोपरान्त वन विभाग व राजस्व विभाग के साथ संयुक्त निरीक्षण कराने के उपरान्त ही पत्रावली गठित कर आॅन लाइन अपलोड की जायेगी। -- as on 21-Feb-2024
Physical Peramenters